Analysis of Material Requirement Planning for Pentolite Production (Case Study: Indonesia’s Explosives Manufacturing)

Authors

  • Verani Hartati Industrial Engineering, Faculty of Engineering - Widyatama University Author
  • Sa’durrifki Industrial Engineering, Faculty of Engineering - Widyatama University Author

Keywords:

EOQ, LFL, MRP, POQ

Abstract

A company engaged in manufacturing explosives produces several products, one of which is pentolite. This product is commonly used as primary blasting material for use in mining operations. Fluctuating coal exports affect the demand for pentolite, in addition to the dominant source of imported raw materials, which requires companies to make proper planning for the needs of pentolite raw materials. Material Requirement Planning (MRP) is an inventory planning and scheduling technique used to manage the manufacturing process, this method is appropriate because it can optimize inventory, reduce the risk of delays and increase efficiency. Several lot- sizing techniques will be used in this study to obtain the optimal order size at the lotting stage in MRP. The techniques used are lot for lot (LFL), economic order quantity EOQ), and period order quantity (POQ). The results show that for both P and T raw materials, the lot-sizing technique that gives the smallest inventory cost results is to use the period order quantity.

Downloads

Download data is not yet available.

References

Balakrishnan, A. and J. Geunes, Requirements planning with substitutions: exploiting bill-of- materials flexibility in production planning. Manufacturing & Service Operations Management, 2000. 2(2): p. 166-185.DOI: https://doi.org/10.1287/msom.2.2.166.12349.

Mula, J., R. Poler, and J.P. Garcia-Sabater, Material requirement planning with fuzzy constraints and fuzzy coefficients. Fuzzy Sets and Systems, 2007. 158(7): p. 783-793.DOI: ttps://doi.org/10.1016/j.fss.2006.11.003.

Berchet, C. and G. Habchi, The implementation and deployment of an ERP system: An industrial case study. Computers in industry, 2005. 56(6): p. 588-605.DOI: https://doi.org/10.1016/j.compind.2005.02.009.

Asmal, S., et al. Green inventory controlling analysis of coal using the lot sizing technique: Lesson learned form nickel mining industry. IOP Publishing.

Khan, M., M.Y. Jaber, and M. Bonney, An economic order quantity (EOQ) for items with imperfect quality and inspection errors. International Journal of Production Economics, 2011. 133(1): p. 113-118.DOI: https://doi.org/10.1016/j.ijpe.2010.01.023.

Louly, M.-A. and A. Dolgui, Optimal MRP parameters for a single item inventory with random replenishment lead time, POQ policy and service level constraint. International Journal of Production Economics, 2013. 143(1): p. 35-40.DOI: https://doi.org/10.1016/j.ijpe.2011.02.009.

Downloads

Published

2022-01-30

How to Cite

Hartati, V., & , S. (2022). Analysis of Material Requirement Planning for Pentolite Production (Case Study: Indonesia’s Explosives Manufacturing). CENTRAL ASIA AND THE CAUCASUS, 23(1), 1320-1328. https://ca-c.org/CAC/index.php/cac/article/view/173

Plaudit