Supplier Selection Criteria: A Case in Selecting Best Supplier for Industrialised Building System (IBS) Construction Project

Authors

  • Mazri Yaakob Disaster Management Institute (DMI), School of Technology Management and Logistics, Universiti Utara Malaysia, Malaysia Author
  • Mohd Nasrun Mohd Nawi Disaster Management Institute (DMI), School of Technology Management and Logistics, Universiti Utara Malaysia, Malaysia Author
  • Mohd Faizal Omar School of Quantitative Science, Universiti Utara Malaysia, Malaysia. Author

Keywords:

supplier selection, Industrialized Building System (IBS), criteria, Supply Chain Management (SCM)

Abstract

 Supplier selection is the most important activities in construction supply chain, especially in Industrialised Building System (IBS) construction where most of the building component are not manufactured in construction site. There is a need for accurate decision in supplier selection, which is essential nowadays with the increasingly competitive environment. Inaccurate selection could lead to serious construction problems, such as project delay, and cost overrun. Moreover, with the existence high numbers of criteria and suppliers available, the supplier selection process for a specific project needs becoming more difficult. An interview session was conducted among three decision makers (DMs), then selected the relevant and critical criteria and sub-criteria of a IBS supplier that has been identified from various literature. As a result, cost (total cost and term of payment) and capability (design, problem treatment and mobility) are the most influence criteria and sub-criteria that has been highlighted.

Downloads

Download data is not yet available.

References

Cidb, Construction Industry Transformation Programme 2016-2020 (CITP 2016-2020), 1-4. 2015, CIDB Publishing Kuala Lumpur.

Mohd Salleh, S.S.M., et al., Internal and external top management team (TMT) networking for advancing firm innovativeness. Polish Journal of Management Studies, 2018. 18(1): p. 311-325 DOI: https://doi.org/10.17512/pjms.2018.18.1.23.

Gann, D.M., Construction as a manufacturing process? Similarities and differences between industrialized housing and car production in Japan. Construction Management & Economics, 1996. 14(5): p. 437-450 DOI: https://doi.org/10.1080/014461996373304.

Willis, T.H., C.R. Huston, and F. Pohlkamp, Evaluation measures of just-in-time supplier performance. Production and Inventory Management Journal, 1993. 34(2): p. 1.

Yadav, A.K., Emerging Opportunities In Planning & Review Of Inventory Control in Hotel Industries. Multidisciplinary Higher Education, Research, Dynamics & Concepts: Opportunities & Challenges For Sustainable Development (ISBN 978-93-87662-12-4), 2018. 1(1): p. 126-138.

Carr, A.S. and L.R. Smeltzer, The relationship of strategic purchasing to supply chain management. European Journal of Purchasing & Supply Management, 1999. 5(1): p. 43-51 DOI: https://doi.org/10.1016/S0969-7012(98)00022-7.

Rezaei, M., M. Naeeni, and M. Motlagh, Integrated Fuzzy ANP, Fuzzy VIKOR and goal programming for sourcing in a supply chain: A case study from cable industry. Decision Science Letters, 2013. 2(4): p. 287-298.

Ho, W., X. Xu, and P.K. Dey, Multi-criteria decision making approaches for supplier evaluation and selection: A literature review. European Journal of operational research, 2010. 202(1): p. 16-24 DOI: https://doi.org/10.1016/j.ejor.2009.05.009.

Van der Vaart, T. and D.P. Van Donk, A critical review of survey-based research in supply chain integration. International journal of production economics, 2008. 111(1): p. 42-55 DOI: https://doi.org/10.1016/j.ijpe.2006.10.011.

Agarwal, P., et al., A review of multi-criteria decision making techniques for supplier evaluation and selection. International journal of industrial engineering computations, 2011. 2(4): p. 801-810 DOI: https://doi.org/10.5267/j.ijiec.2011.06.004.

Haldar, A., et al., An integrated approach for supplier selection. Procedia engineering, 2012. 38: p. 2087-2102 DOI: https://doi.org/10.1016/j.proeng.2012.06.251.

Vrijhoef, R. and L. Koskela, The four roles of supply chain management in construction. European journal of purchasing & supply management, 2000. 6(3-4): p. 169-178 DOI: https://doi.org/10.1016/S0969-7012(00)00013-7.

Othman, A.A. and S. Abd Rahman, Supply chain management in the building construction industry: Linking procurement process coordination, market orientation and performance. Journal of Surveying, Construction and Property, 2010. 1(1) DOI: https://doi.org/10.22452/jscp.vol1no1.2.

Meng, X., The effect of relationship management on project performance in construction. International journal of project management, 2012. 30(2): p. 188-198 DOI: https://doi.org/10.1016/j.ijproman.2011.04.002.

Lu, M. and Y. Geyao. The selection of construction material suppliers in supplier relationship management (SRM). IEEE DOI: https://doi.org/10.1109/ISME.2010.247.

Ho, W., P.K. Dey, and M. Lockström, Strategic sourcing: a combined QFD and AHP approach in manufacturing. Supply Chain Management: An International Journal, 202(1), 16–24, 2011 DOI: https://doi.org/10.1108/13598541111171093.

Aretoulis, G.N., G.P. Kalfakakou, and F.Z. Striagka, Construction material supplier selection under multiple criteria. Operational Research, 2010. 10(2): p. 209-230 DOI: https://doi.org/10.1007/s12351-009-0065-3.

Scott, D., Critical realism and empirical research methods in education. Journal of philosophy of education, 2005. 39(4): p. 633-646 DOI: https://doi.org/10.1111/j.1467-9752.2005.00460.x.

Schramm, F. and D.C. Morais, Decision support model for selecting and evaluating suppliers in the construction industry. Pesquisa Operacional, 2012. 32: p. 643-662 DOI: https://doi.org/10.1590/S0101-74382012005000020.

Carroll, J.S., Management Research: An Introduction. Management Learning, 2003. 34(2): p. 262 DOI: https://doi.org/10.1177/1350507603034002007.

AbdelHamid, M.S., et al., Identification of supplier selection criteria and risk approach for Egyptian contractors. Int. J. Emerg. Technol. Adv. Eng, 2014. 4(2).

Downloads

Published

2024-07-22

How to Cite

Yaakob, M., Nawi, M. N. M., & Omar, M. F. (2024). Supplier Selection Criteria: A Case in Selecting Best Supplier for Industrialised Building System (IBS) Construction Project. CENTRAL ASIA AND THE CAUCASUS, 22(5), 142-150. https://ca-c.org/CAC/index.php/cac/article/view/752